ABS’ scope
of classification for an FPSO includes:
- Review
and approval of the FPSO design for compliance with ABS
Rules
- Survey
of fabrication components in the field to facilitate compliance
with ABS Rules
- Survey
of the offshore hook-up and commissioning to ready for
first oil
A fully
classed unit includes oversight of the:
- Hull
structure
- Mooring
systems and foundations
- All
marine, production, utility and safety systems
ABS also
can certify the subsea components, including risers, flowlines
and umbilicals. With regard to these five conversions, the
Brasil and Fluminense will incorporate a turret
mooring system. The P43, P48 and P50 will have a DICAS (Differentiated
Compliant Anchoring System) spread mooring system, developed
by the Petrobras Research Center (CENPES).
The Brasil
is the first scheduled for delivery, with installation in
the Campos Basin expected to commence in September 2002. First
oil is slated later this year.
"One
of the biggest class challenges with this project has been
the short conversion timeframe of 17 months from project start
in June 2001 to first oil in October 2002. ABS experienced
additional challenges due to the project’s worldwide spread
of activities," said Pacheco.
ABS’ London
office completed analysis on the Brasil conversion,
gaining valuable experience executing a full SafeHull assessment
necessary for assignment of the SH (CS) notation.
Owned
and operated by SBM for Petrobras, the FPSO Brasil
will have a design capacity of 90,000 barrels of oil per day,
with five of the six wells previously operating with the P36
planned for tie-in.
The
P43, P48 and P50 are key projects for the Brazilian energy
giant. The FPSOs P43 and the P48 are each capable of storing
1 million barrels of oil and processing 150,000 barrels/day
of crude oil. For conversion of the P48, Petrobras used the
ABS-classed VLCC Stena Concordia. Petrobras used the
sister vessel, Stena Continent, also ABS-classed, for
the P43.
Petrobras
will use the ABS-classed VLCC Felipe Camarão
for the P50 conversion. The unit is planned for the Campos Basin deepwater Albacora Leste Field, with production from the 180,000 barrels/day FPSO scheduled to begin in 2004. This field is a significant contributor to Brazil’s total oil output, which in May reached 1.53 million barrels per day.
Unlike
previous conversions, for the P50, Petrobras, has awarded
contracts for the various modules of the production facilities
and accommodations to different suppliers. Main contractor,
Jurong Shipyard, will assemble the modules to complete the
conversion.
"This
approach presents management challenges for the unit’s classification;
however, working with clients on fast-track fabrication and
installation schedules with various contractors and vendors
is nothing new to ABS. As the leader in offshore classification,
and with decades of in-country experience, we’re accustomed
to supporting the timely start-ups of these complex logistical
projects," said Pacheco.
Finally,
the Sahara—one of the 15 largest tankers in the world
with an oil storage capacity of 1.3 million barrels —is being
used for the Fluminense FPSO conversion. MODEC International
is the owner/operator for this unit, which is due for delivery
first quarter 2003. Also destined for Campos Basin, the Fluminense
will serve as the hub for the Bijupira and Salema Fields.
|